Road Repair continued

Ricky Tillman has done an excellent job. As the work was progressing, we added several items, resulting in a total cost of $600, an increase of $150. This is an amazing bargain for the work that was done. Added items included: widening of road by 8 feet at this uphill stretch to allow for better sun drying after a rain, 3 washout basins near new cross road trenches (each with multiple boulders), several spot patches between gate and damaged area. See Youtube video. If you have not visited your property recently, this is a great time.

Friday, August 15, 2014

Road Repair

Continued rains over the past week have made the erosion at this section dangerous. This photo shows me at a depth of 18 inches ... enough to flip a vehicle or break an axle. Other areas are knee deep. Repair is urgent. I have contracted with Ricky Tillman for $450 to create a diversion channel above the erosion and put on a new layer of stone. I will pay up front, but hopefully everyone will be willing to chip in to share the cost.

Tuesday, August 12, 2014

Road Damage

Erosion of road surface has progressed. The heavy rains this spring are causing more damage. This area could become impassable soon if not repaired. Drive slowly on this stretch to avoid more scattering of rocks.